淡江大橋大事記
1998年 完成規劃報告
Completion of planning report
1999年 有條件通過環境影響評估
Conditional passage of EIA
2000年 改採政府編列預算方式辦理
Change to
implementation with a government budget
2006年 規劃檢討作業
Planning review
tasks
2013年 通過第1次環境影響差異分析,啟動環境監測
Passes first
environmental impact discrepancy analysis; initiation of environmental monitoring
‧委託淡江大橋第三標專案管理(PCM)—林同棪工程顧問公司辦理第3標(主橋段)橋型評選等作業
‧先行辦理對生態、環境及文化資產較無影響,且無用地問題路段之設計施工,以加速推動本計畫
‧成立環境保護監督小組
‧「淡江大橋及其連絡道路新建工程」(第1標)開工
‧ The "Danjiang Bridge and its
access road construction plan" is approved
‧Hiring of the T.Y. Lin Engineering
Consultants Co., Ltd. to conduct bridge type selection tasks etc. for the 3rd tender
(main bridge section).
‧To accelerate project progress,
preliminary implementation of design and construction work for sections where
there are no impacts on ecology, environment, or cultural assets, and no
available land problems.
‧Establishment of an environmental
protection supervisory team
‧Start of work on the "Construction
of Danjiang Bridge and Connecting Road Network" (1st tender)
2015年 完成國際競圖作業
‧辦理水中、陸域文化資產調查計畫及3項生態研究計畫
‧辦理八里端及淡水端連絡道工程設計
Completion of
international drawing competition tasks
‧Implementation of an aquatic and
terrestrial cultural asset survey project and three ecological research
projects.
‧Implementation of engineering design
for access roads on the Bali and Tamsui sections.
2016年 ‧「淡江大橋及其連絡道路新建工程」(第1標)完工
‧「淡江大橋及其連絡道路新建工程」(第2標)開工
‧ Completion of the "Construction of
Danjiang Bridge and Connecting Road Network" (1st tender)
‧Start of work on the "Construction
of Danjiang Bridge and Connecting Road Network" (2nd tender)
2017年 通過第2次環境影響差異分析(橋型確定)
Passage of 2nd
environmental impact discrepancy analysis (confirmation of bridge type)
2018年 ‧行政院核定「淡江大橋及其連絡道路建設計畫」修正
‧「淡江大橋及其連絡道路新建工程」(第3標)決標簽約
‧The Executive Yuan approves the revised "Danjiang Bridge
and its Access Road Construction plan"
‧ Award of tender and contract signing for the "Construction
of Danjiang Bridge and Connecting Road Network" (3rd tender)
2019年 「淡江大橋及其連絡道路新建工程」(第3標)開工
Start of work on "Construction of Danjiang Bridge and
Connecting Road Network" (3rd tender)
2021年 預計「淡江大橋及其連絡道路新建工程」(第2標)完工
Expected completion of the "Construction of Danjiang
Bridge and Connecting Road Network" (2nd tender)
2024年 預計全線完工通車
Expected completion and opening of full route
防汛作業無缺口
工安要求無災害
進度要求均達標